Two articles from Catching Wind, a newsletter published by RENEW Wisconsin with funding from a grant from the U.S. Department of Energy:
State’s Hostility Toward Renewables Escalates
At the urging of Wisconsin utilities, several lawmakers have introduced a bill to allow a renewable energy credit (REC) to be banked indefinitely. If adopted, this measure (AB146) would constitute the most devastating legislative assault yet on the state’s renewable energy marketplace, which is already reeling from the suspension of the statewide wind siting rule this March and the loosening of renewable energy definitions to allow Wisconsin utilities to count electricity generated from large Canadian hydro projects toward their renewable energy requirements.
“Leaders” Lag Citizenry on Wind Support
Public support for wind energy development has held strong against the attacks launched by Governor Walker and the Legislature’s new Republican majority, according to a poll conducted between April 11 and April 18 by the St. Norbert College Survey Center for Wisconsin Public Radio.
Asked whether Wisconsin should "increase, decrease or continue with the same amount" of energy supply from various sources, 77% favored increasing wind power, the highest of any option (60% favored increasing hydropower, 54% biomass, 39% natural gas, 27% nuclear, and 19% coal).
Showing posts with label Hydro. Show all posts
Showing posts with label Hydro. Show all posts
Thursday, June 23, 2011
Friday, June 10, 2011
Genoa nuclear waste set to move to dry casks
From an article by Chris Hubbuch in the Winona Daily News:
Dairyland Power will begin removing spent fuel from its Genoa, Wis., nuclear plant and encasing it in steel and concrete casks later this spring, nearly a quarter century after the plant ceased operations.
Though the federal government has no immediate plans to take possession of the radioactive waste, the move to store it temporarily on site should cut by two-thirds the power cooperative's cost to staff the plant and speed up the decommissioning process, expected to take another seven years and bring decommissioning costs to an estimated $79 million.
It's a scenario that Dairyland's founders couldn't have envisioned in 1941, when they banded together to create a network to provide reliable electric power to rural Wisconsin.
But those founders were thinking about the future, said Dairyland president William Berg, who encouraged some 700 delegates of Dairyland's members to continue building value during his address at the cooperative's 70th annual meeting Wednesday.
That means building a system with the capacity to meet future needs while preserving the environment and embracing renewable energy sources when the future of coal - the basis for most of today's power - is in question.
Dairyland now generates about 11 percent of its electricity with renewables such as wind, hydro and biomass-fueled generators. Berg said the company is on track to meet its goal of 25 percent by 2025.
Dairyland Power will begin removing spent fuel from its Genoa, Wis., nuclear plant and encasing it in steel and concrete casks later this spring, nearly a quarter century after the plant ceased operations.
Though the federal government has no immediate plans to take possession of the radioactive waste, the move to store it temporarily on site should cut by two-thirds the power cooperative's cost to staff the plant and speed up the decommissioning process, expected to take another seven years and bring decommissioning costs to an estimated $79 million.
It's a scenario that Dairyland's founders couldn't have envisioned in 1941, when they banded together to create a network to provide reliable electric power to rural Wisconsin.
But those founders were thinking about the future, said Dairyland president William Berg, who encouraged some 700 delegates of Dairyland's members to continue building value during his address at the cooperative's 70th annual meeting Wednesday.
That means building a system with the capacity to meet future needs while preserving the environment and embracing renewable energy sources when the future of coal - the basis for most of today's power - is in question.
Dairyland now generates about 11 percent of its electricity with renewables such as wind, hydro and biomass-fueled generators. Berg said the company is on track to meet its goal of 25 percent by 2025.
Labels:
Biomass,
Generation,
Hydro,
Nuclear,
Southwest Wisconsin,
Wind
Thursday, May 26, 2011
Energy groups oppose bill to undermine Wisconsin's renewable energy commitment
From statements issued by three groups in opposition to Assembly Bill 146:
"Clearly, this bill is a drastic step in the wrong direction for our state. The Wisconsin Energy Business Association therefore opposes this attack on renewable energy in our state." - Wisconsin Energy Business Association. Full statement.
We strongly recommend that this bill not be approved as it solves no known problem in Wisconsin and seeks only to roll-back policies on renewable energy that have served the state well and are otherwise benefitting Wisconsin residents with cleaner air and lower prices for electricity. - Wind on the Wires. Full statement.
Fresh attack on Wisconsin voters’ desire for a renewable energy standard would kill wind projects and sap state’s economy, say wind energy advocates - American Wind Energy Association. Full statement.
"Clearly, this bill is a drastic step in the wrong direction for our state. The Wisconsin Energy Business Association therefore opposes this attack on renewable energy in our state." - Wisconsin Energy Business Association. Full statement.
We strongly recommend that this bill not be approved as it solves no known problem in Wisconsin and seeks only to roll-back policies on renewable energy that have served the state well and are otherwise benefitting Wisconsin residents with cleaner air and lower prices for electricity. - Wind on the Wires. Full statement.
Fresh attack on Wisconsin voters’ desire for a renewable energy standard would kill wind projects and sap state’s economy, say wind energy advocates - American Wind Energy Association. Full statement.
Tuesday, May 10, 2011
Boston firm aims to harness river power by 2017
From an article by Steve Cahalan in the La Crosse Tribune:
A Massachusetts company hopes to develop hydroelectric projects at nine upper Mississippi River lock and dam sites by 2017, officials said Monday.
Free Flow Power Corp., a 3-year-old Boston firm, plans to apply for federal licenses for hydropower projects that in this area include Lock and Dam 4 at Alma, Lock and Dam 6 at Trempealeau, Lock and Dam 7 near Dresbach, Minn., and Lock and Dam 9 near Lynxville.
The nine projects could meet the electricity needs of 65,000 homes, company officials told about 40 people at a public informational meeting at the Radisson Hotel in La Crosse.
Each project would have one of three designs — a traditional hydroelectric powerhouse that would be built on the end of the dam and contain turbines; a “gate bay installation” alternative with turbines installed in front of or behind existing dam gates; or a system with turbines installed at the bottom of the auxiliary lock. Studies would determine which design would be best for a particular lock and dam.
The Federal Energy Regulatory Agency will accept written comments in the next 60 days on what studies should be required during Free Flow Power’s licensing process.
Officials of various state and federal agencies accounted for most of the people at Monday’s 2½-hour session. But a few members of the public also spoke, including retired boat captain Byron Clements of Genoa, who questioned the feasibility of hydroelectric power on the Mississippi.
“I don’t think they can make it work and make money at it,” Clements said after the meeting. Clements, who with his wife operates Captain Hook’s Bait & Tackle shop in Genoa, said he also is concerned about fish being killed by the turbines.
The proposed turbines would turn much slower than those traditionally used in major hydroelectric projects in the western United States, said Jack Batchelder, a Free Flow Power environmental scientist.
A Massachusetts company hopes to develop hydroelectric projects at nine upper Mississippi River lock and dam sites by 2017, officials said Monday.
Free Flow Power Corp., a 3-year-old Boston firm, plans to apply for federal licenses for hydropower projects that in this area include Lock and Dam 4 at Alma, Lock and Dam 6 at Trempealeau, Lock and Dam 7 near Dresbach, Minn., and Lock and Dam 9 near Lynxville.
The nine projects could meet the electricity needs of 65,000 homes, company officials told about 40 people at a public informational meeting at the Radisson Hotel in La Crosse.
Each project would have one of three designs — a traditional hydroelectric powerhouse that would be built on the end of the dam and contain turbines; a “gate bay installation” alternative with turbines installed in front of or behind existing dam gates; or a system with turbines installed at the bottom of the auxiliary lock. Studies would determine which design would be best for a particular lock and dam.
The Federal Energy Regulatory Agency will accept written comments in the next 60 days on what studies should be required during Free Flow Power’s licensing process.
Officials of various state and federal agencies accounted for most of the people at Monday’s 2½-hour session. But a few members of the public also spoke, including retired boat captain Byron Clements of Genoa, who questioned the feasibility of hydroelectric power on the Mississippi.
“I don’t think they can make it work and make money at it,” Clements said after the meeting. Clements, who with his wife operates Captain Hook’s Bait & Tackle shop in Genoa, said he also is concerned about fish being killed by the turbines.
The proposed turbines would turn much slower than those traditionally used in major hydroelectric projects in the western United States, said Jack Batchelder, a Free Flow Power environmental scientist.
Thursday, March 11, 2010
Workshop: Renewable energy for international development, Costa Rica, May 15-24, 2010
From a course description from Madison Area Technical College:
Course Number 20-623-290-090 Class Number 61386
Three Credits Hybrid Format (Study Abroad + Online)
May 15–24, 2010
Renewable Energy for International Development provides an examination of energy and economics in developing countries with special consideration given to renewable energy sources. The course will combine 8-weeks of online instruction with 10 days of travel and study abroad in Costa Rica. Students will learn to specify, design, and install renewable energy systems for developing countries. Field work will include design and installation of one or more of the following types of renewable energy systems:
+Small solar electric system (<200W off-grid)
+Micro-Hydropower generator (<2kW)
+Small scale wind generator (<1kW)
+Solar thermal hot water system
Course Number 20-623-290-090 Class Number 61386
Three Credits Hybrid Format (Study Abroad + Online)
May 15–24, 2010
Renewable Energy for International Development provides an examination of energy and economics in developing countries with special consideration given to renewable energy sources. The course will combine 8-weeks of online instruction with 10 days of travel and study abroad in Costa Rica. Students will learn to specify, design, and install renewable energy systems for developing countries. Field work will include design and installation of one or more of the following types of renewable energy systems:
+Small solar electric system (<200W off-grid)
+Micro-Hydropower generator (<2kW)
+Small scale wind generator (<1kW)
+Solar thermal hot water system
Labels:
Hydro,
Solar electricity,
Solar hot water,
Southwest Wisconsin,
Wind
Monday, December 21, 2009
Angelo dam could produce power again
From an article in The Tomah Journal:
SPARTA - A dam that hasn’t produced power in about 40 years could be fired up again to provide alternative electricity and education for Western Technical College.
“It is a diamond in the rough that has been overlooked for a long time,” said Stephen Doret, a hydroelectric consultant and chief engineer for Mill Road Engineering in Westborough, Mass.
Doret detailed plans for the Angelo Pond dam on the La Crosse River at a public hearing Monday at Western’s Sparta campus.
The dam would generate electricity for the Sparta campus and help train students about emerging technology fields, said Mike Pieper, Western’s vice president of finance and operations.
The re-powered dam is expected to crank out about 1 million kilowatt hours a year, far more than the 250,000 kilowatt hours the Sparta campus annually uses, said Doret.
SPARTA - A dam that hasn’t produced power in about 40 years could be fired up again to provide alternative electricity and education for Western Technical College.
“It is a diamond in the rough that has been overlooked for a long time,” said Stephen Doret, a hydroelectric consultant and chief engineer for Mill Road Engineering in Westborough, Mass.
Doret detailed plans for the Angelo Pond dam on the La Crosse River at a public hearing Monday at Western’s Sparta campus.
The dam would generate electricity for the Sparta campus and help train students about emerging technology fields, said Mike Pieper, Western’s vice president of finance and operations.
The re-powered dam is expected to crank out about 1 million kilowatt hours a year, far more than the 250,000 kilowatt hours the Sparta campus annually uses, said Doret.
Friday, June 5, 2009
Hospital aims for new energy project
A story from WEAU News:
A western Wisconsin hospital wants to harness some of the mighty Mississippi’s power for its own energy needs.
Gundersen Lutheran Hospital is hoping to get approved to build seven hydrokinetic turbines at a Mississippi River dam, which the hospital says would provide about 90% of its energy needs. The hospital says it would take millions of dollars to create, and would use a local power company to convert the power. It's in the permit stages now, which the hospital says could take three years.
"Versus wind which you never know whether the wind is going to be blowing or the sun is going to be shining so we think that this is a really good alternative as a renewable energy source," says Jeff Rich with Gundersen Lutheran.
Rich says the hospital could recoup the cost of the project in about ten years.
A western Wisconsin hospital wants to harness some of the mighty Mississippi’s power for its own energy needs.
Gundersen Lutheran Hospital is hoping to get approved to build seven hydrokinetic turbines at a Mississippi River dam, which the hospital says would provide about 90% of its energy needs. The hospital says it would take millions of dollars to create, and would use a local power company to convert the power. It's in the permit stages now, which the hospital says could take three years.
"Versus wind which you never know whether the wind is going to be blowing or the sun is going to be shining so we think that this is a really good alternative as a renewable energy source," says Jeff Rich with Gundersen Lutheran.
Rich says the hospital could recoup the cost of the project in about ten years.
Subscribe to: